|
|
Admitting Mistakes
If there are any perfect project managers out there, I
haven’t heard of them yet. Even the most famous and successful project managers
made mistakes. The difference between these folks and some others was their
reaction to their mistake. They didn’t pretend it didn’t happen; they
confronted the mistake, made corrections and got on with it. That’s how they
gained their goals. To do this they kept the focus on the project and achieving
its goals and not on their reputations. Mature executives expect everyone to
slip up occasionally. What they don’t expect and can’t afford is people who try
to cover up their mistakes and fail to learn from them.
The first step in the process is to recognize when a mistake
has been made. The symptom will be a variance between project results and your
project plan. The variance may not necessarily be that the project has gotten
behind schedule, or that the project is over budget. It may be that a team
member or group of members are working 10 or 12 hour days for work you allowed
8 hours for, or are producing an unexpectedly high number of defects and
re-work. You’ll recognize these symptoms by the background noise consisting of
team member complaints.
There are some mistakes that are commonly made by project managers.
There is a fairly comprehensive list and description in a set of articles on
the three O website: Common PM Mistakes. If you would like more background on
what to look for, I suggest reading these articles. This article is not about
identifying mistakes, but what to do once you’ve identified a mistake. Keep in
mind that the mistakes I’m referring to here are ones you’ve made, not mistakes
team members or stakeholders have made.
Do not try to cover the mistake up and hope the project
completes before anyone notices. You may be the first to notice because of your
proximity to the project, but others will notice before long, either because of
the results you report or because the problems worsen. Take ownership of the
mistake. You are in the best place to correct the mistake, or at least to
identify the proper corrective action, so it stands to reason that you should
own the mistake. Analyze the mistake. Identify what went wrong and why. You may
want to perform some root cause analysis on your own at this point. Trace back
to the root cause by repeatedly asking yourself "why” until you identify the
root cause. Now identify a corrective action. Ask yourself if the corrective
action can be performed by the team and if so, will it be effective in bringing
the project back on track. If the corrective action can be implemented by you
without any change to the project plans then go ahead and take the action. You
may want to communicate the action you’ve taken to the project sponsor and
team, for example in a "corrective actions taken” portion of your weekly status
report. The one skill that will separate you from the common herd is your
ability to spot the mistake as early as possible. Monitoring the project
through work results and "walk about” management are your best tools for
achieving this. Don’t hesitate to take corrective action once you have
identified a mistake.
Corrective actions that require a change in the project
plans will require a change request. Corrective actions may require an
extension of the schedule, an increase in the budget for additional or
different resources, a reduction in project scope, or some combination of
these. Review the mistake, its impact on the project, the cause of the mistake,
and the recommended corrective action in a sit-down meeting with your project
sponsor. The sponsor may have suggestions of their own to correct the problem
and these may require some thought on your part to determine their
effectiveness. Don’t be afraid to ask for more time to consider their proposal if
you need it. If your sponsor’s corrective action is as good as or better than
yours, adopt it. If not, don’t be afraid to tell the sponsor and explain your
reasons for preferring your corrective action. Point out any risks attendant on
the corrective action and manage these through the risk register.
Once the change request has been composed and approved,
implement the change, changing your project plans and baselines as appropriate.
The change and the reason it is necessary (i.e. your mistake) must be explained
to the team and stakeholders at the next opportunity. This doesn’t require you
to wear a hair shirt and abase yourself before the stakeholders and project
team; treat the mistake dispassionately by explaining the mistake and its
impact on the project in technical terms. Use the "I” pronoun by all means but
don’t overuse it. Everyone should have a thorough understanding of the mistake,
its negative impact on the project, and how it will be corrected. The ideal
opportunity for this communication are team meetings, stakeholder meetings, and
steering committee meetings.
Let’s use an example to illustrate what I mean. Let’s say
you’re managing a project to build a software system using a new development
platform. You’ve planned for the appropriate training, acquired a few SMEs on
the new platform and allowed for a learning curve, but that allowance is
proving to be insufficient; effort and duration estimates are significantly
less than the actual time required to build the system. The cause of this is underestimating
effort, but why was the effort underestimated? The immediate reason would be
unfamiliarity with the new platform, but why were you unfamiliar with it? The
reason might be that insufficient research was done on estimating the learning
curve. For arguments sake, let’s say you accepted the vendor’s word for the
learning curve without further research. So your mistake was not researching
the learning curve sufficiently to support accurate effort estimations for the
work. The reason might be any one of many such as a bad formula for calculating
the effort, or some other reason. The reason doesn’t matter; you’ll identify it
when you perform your Root Cause Analysis. The important thing is the
identification of your mistake. Now you can get on with identifying a
corrective action. Let’s say your charter identifies delivery of the new system
by the deadline as a top priority and delivery to budget as the next highest
priority. Examine the requirements in the Business Requirements Document (BRD)
to determine the lowest priority requirements and drop enough requirements to
allow the project to complete on time, and for the original budget. Now you
have the problem described, identified your mistake, and the corrective action
which will bring the project back on track. Now is the time to call for that
sit down meeting with your project sponsor and explain the problem to them.
Don’t
forget that you must take the appropriate steps to ensure that this mistake
doesn’t get repeated by you or any other project manager in the organization.
The standard vehicle for doing this is Lessons Learned. Do make sure that you
have identified the right root cause and that your corrective action is
effective in addressing it. Using the example above, you need to ensure that all
estimations for future work are accurate, or have been corrected. Verification
of their accuracy would be that work is now being completed to the original
estimate. Now monitor the work closely to ensure it is being completed to plan.
|