Tracking & Oversight
The goal of the Software Project Tracking and Oversight Key
Process Area (KPA) is to provide sufficient insight into project performance so
that the project manager can detect variances between performance and the plan
and take preventive or corrective action. This KPA influences all PMBOK
knowledge areas and is most closely associated with the Monitoring and
Controlling group of processes. As with the other KPAs Software Project
Tracking and Oversight is organized into goals, commitments, abilities,
activities, measurements, and verifications.
Goals
The goals of this KPA relate to and support project
oversight and corrective actions. The goals are that results are tracked
against project plans, that corrective actions are taken when there is a
variance between planned results and actual results, and that corrective
actions that change the project plan are agreed to by the affected groups. The
abilities and activities all support the achievement of these goals.
Commitment to Perform
Commitments to this KPA are required at the executive level.
The first commitment is that a software project manager be assigned to the
project. This commitment will be made by default for most IT projects. The
project manager responsible for the entire project is likely to be someone who
is considered a "software project manager”, or at least has experience managing
software projects. When larger projects require a sub-project for the creation
of a software system or application to be defined, this commitment requires a
project manager to be assigned to manage the sub-project. This is an
organizational commitment, but might require you to identify and assign a
project manager to manage the software sub-project if you are the overall
project manager.
The second commitment is also at the organizational level
and it is that project management follows a written organizational policy for
managing software projects. PMs working out of a PMO or PMC should have such a
policy to follow. If you are a project manager leading the charge for CMM/CMMI
certification you should undertake the writing of this policy to govern your
project and future projects for your organization.
Ability to Perform
There are 5 abilities required to meet CMM/CMMI level 2
criteria. The first ability is that software project has a project plan. The
second is that the software project manager assigns work to the project team.
This means not only that the project manager defines, organizes, and schedules
the work in their plan, but that they direct individual team members to do the
work. I believe that meeting the criteria for this ability requires the
software project manager to be given the authority to direct the project
resources work for the duration of the project. The best way for this authority
to be officially granted is through the Project Charter which governs the
project.
The third ability calls for adequate resources to be
provided for tracking and oversight activities. Planning of the activities will
be supported by the project’s plans and schedule. Adequate funding will be
demonstrated by the budget for resources to perform oversight and tracking
activities being part of the approved project budget. Ability 4 requires the
software project manager to be trained in managing the "technical and personnel
aspects” of the software project. I would argue that there is no better way of
demonstrating this ability than by the certification of the software project
manager as a Project Management Professional (PMP®).
The Project Management Institute oversee this certification and are recognized
globally as the leaders in the area of project management certification and
project management best practices. Certification of your software project
manager is straight forward, providing PMI’s criteria for project management
experience are met. Providing they are, the project manager can choose from a
host of quality PMP® courses or PMP® exam preparation training products to
prepare them for the certification exam. These courses will train project
managers in Project Management best practices and their implementation, as well
as helping the project manager pass their exam.
The final ability calls for first-line software managers to
receive "orientation in the technical aspects of the software project”. CMMI defines
a first-line software manager as someone who has direct management
responsibility, including responsibility for providing technical direction, for
staffing and activities of a single organizational unit. This definition
matches the PMBOK®’s definition of a
functional manager. The first-line manager should be educated in the tools,
processes, procedures, and standards used for the project.
Activities
Activities called for by CMM include:
- Use the project plan for tracking
activities and communicating project status. The plan should be updated
with information for work completed and made available to project stakeholders.
Your MS Project file will satisfy this criterion and will convert your
WBS/schedule to several formats that can be accessed by stakeholders who do not
have MS Project on their desktop.
- The project plans are revised according to
a documented procedure. This procedure will be your Change Management plan,
or Integrated Change Control System (ICCS). The various components of the
project plan specify how changes approved by the ICCS/Change Management plan
are to be implemented. The activity also calls for a review of the revised
project plan.
- Commitments made to external groups, and
any changes to those commitments, are reviewed with senior management according
to a documented procedure. In the context of tracking and oversight this
activity will be described in the project’s Change Management plan.
- Approved changes to the software project
are communicated to the members of the software engineering group and other
software-related groups. Your Change Management plan, or Communications
Management plan, should describe this.
- The sizes of work products, or changes to
the work products are tracked and corrective actions taken as necessary.
CMM uses the word "size” to refer to the number of lines of code, .html pages,
or pages of documentation produced. The idea is to compare the actual size with
the estimates for the purpose of identifying actions required to correct the
estimation procedure and future estimates.
- Effort and costs are tracked and corrective
actions taken when necessary. The cost management portion of the project
plan will govern monitoring and controlling expenditures and identify how
corrective actions are to be identified. The Change Management plan governs how
changes to the cost estimates are to be made. Since software development
projects frequently aren’t governed directly by budgets, this may be
accomplished in the Time Management plan for the project.
- Critical computer resources are tracked and
corrective actions taken when necessary. These will be tracked, along with
other project resources, in the resource management plan.
- The schedule is tracked and corrective
actions taken when necessary. The Time Management portion of the project
plan will describe how this happens, including the analysis of late and early
delivery dates on the plan.
- Technical activities are tracked and
corrective action taken when necessary. Technical activities refer to the
methods, procedures, and processes used to develop and test the software.
Testing activities will be described in the Quality Management plan. Most of
the methods, procedures, and processes associated with development of the
software should be captured in the Configuration Management plan. Activities
not covered by the Configuration Management or Quality Management plans should
be described in a separate plan.
- Project risks are tracked. This is
accomplished by the Risk Management plan
- Measurement data and re-planning data are recorded. This
includes estimates and data associated with the estimates, plus data measuring
completed work. Estimates will be captured in the WBS and schedule. Estimating
tools and methods such as Function Point Analysis (FPA) will be described
elsewhere.
- The software engineering group conducts
periodic internal reviews to track technical progress, plans, performance, and
issues against the plan. The software engineering group includes the
first-line managers and software project manager. This activity is covered by your
weekly status review meetings.
- Formal reviews to address accomplishments
and results are conducted at selected project milestones. These formal
reviews will correspond to your Gate Reviews.
Measurement and Analysis
The effort required to perform the tracking activities is
measured.
Verification
Verification is performed by senior management who review
the tracking and oversight activities periodically. This will be satisfied with
the Gate Reviews planned for the project and by any Steering Committee or Project
Sponsor reviews scheduled. Verification is also done by the project manager.
This requirement can be satisfied with regular status review meetings in
addition to the Gate Meetings. These two verifications also require you to
produce a status report after each meeting.
The 3rd verification calls for reviews or audits
of the project by a Quality Assurance group. Since CMM regards the Quality
Assurance group as an entity outside of the control of the project, the senior
management of your organization should be responsible for this verification. If
you are assigned to manage the project by a PMO or PMC this group may provide
the audits or reviews required by CMM.
|