CPI and Time Sheets
Performance reporting in the area of Earned Value Management
is frequently focused on performance to schedule on software projects to the
exclusion of performance to budget. This occurs for one of two reasons: the
inability of the project to report on performance to budget and a lack of
interest in performance to budget. Lack of interest does not necessarily
indicate a lack of financial responsibility or accountability on the part of
the sponsors; labour accounts for over 95% of the costs on most software
projects and if the team is on schedule we can expect the project to be running
on budget. This assumption is fairly safe so long as the team size remains
constant, team members all cost the same (i.e. their loaded labour rate is the
same), and there is no overtime involved. As soon as any of these elements are
introduced, performance to schedule and performance to budget can diverge.
Let me give you an example to illustrate my point. Let’s
take the example of a software project which will introduce a new system in an
accounting organization. No hardware is involved. The software is being
developed in-house so no new software licenses need to be purchased. Project
costs are almost all generated by payroll. So long as the project is on schedule
and the hours of work planned are accomplishing the work to schedule, both
schedule and budget goals are being met. Now let’s look at the same project
when it falls behind schedule and the programmers work overtime to make up for
lost time. Let’s assume that the time to be made up is 200 hours. Programmer
salaries average $40 per hour so overtime is an extra $20 per hour. The loaded
labour rate is $80 per hour so the cost of the overtime is $100 per hour x 200
hours, or $20K. The project is back on schedule but the overtime has put the
cost $20K over budget. Some of this money can be recovered if the programmers
don’t start charging time to the project until they start their work. This
means that instead of $20K over budget the project will be $4K over budget ($20
per hour x 200 hours).
MS Project will always be your choice of tool to track
schedule performance. The formula for calculating the Schedule Performance
Index (SPI) changes slightly because the BCWP (Budgeted Cost of Work Performed,
or Earned Value) and BCWS (Budgeted Cost of Work Scheduled, or Planned Value)
are no longer measured in dollars. MS Project is capable of measuring the cost
of the work provided the loaded labour rate is provided and MS Project is
updated with the actual hours spent on the work. The loaded labour rate may not
be easily available from the Finance organization – they may not have perceived
a need to calculate this figure or may not have calculated it for the resources
you are tracking. Keeping MS Project up to date with actual hours worked, which
is needed to calculate the Actual Cost of the Work Performed (AC or ACWP), will
be difficult and will mean the project manager must succeed in having the team
use the MS Project file as a time sheet.
Let’s take the same example when there is a difference in
the loaded labour rates for different functions. Let’s say the loaded labour
rate for business analysts is $100 per hour while the loaded labour rate for
programmers is $80 per hour. The project falls 200 hours behind schedule due to
late delivery of specifications and instead of 1000 hours of effort and
duration the business analysts have devoted 1200 hours to the work. The cost of
the business analysts’ work exceeds the budget by $20K ($120K vs. $100K). Now
look at the project performance after the programmers work the overtime to
bring the project back on schedule. The project is on schedule (planned work =
actual work) but over budget because the actual cost of the work exceeds the
planned cost.
Now let’s fast forward to the end of the build and assume
the time recovered by the programmers working overtime was sufficient to
preserve the project schedule and no more corrective actions were necessary.
Let’s say the total programming hours planned was 2000. The actual number of
hours worked was 2000 but 200 of those were worked at the overtime rate which
is $20 per hour more than the loaded labour rate. The total budget for
programming was $80 per hour x 2000 hours, or $160K. The actual cost was $160K
+ ($20 per hour x 200 hours) = $164K. Total actual cost = $284K ($120K +
$164K), total planned cost = $260K ($100K + $160K). Even though the project is
back on schedule, it is over budget and the only way to correct that is to save
$24K somewhere else in the project.
This example points out a problem with using the Earned
Value method to track progress to schedule. Using costs, both actual and
planned to calculate the SPI of a project can be misleading. Calculating the
SPI using the BCWP/BCWS, or EV/PV formula might tell you that the project is
behind schedule when it is actually on schedule, but over budget. Using MS
Project to calculate the SPI using the formula scheduled duration of
work/actual duration of work will tell you if your project is on schedule or
not. Using the effort from MS Project will yield the same results, providing MS
Project is not used as a time sheet. Using effort in place of duration allows
you to weight the work according to the number of resources devoted to it. The
impact of work that goes 1 week over scheduled and takes 10 people to perform
will have 10 times the impact of work that only takes 1 person.
Accurately kept time sheets and the capture of loaded labour
rates in your MS Project file are the answer to accurately calculating the CPI
(Cost Performance Index) of your project. Capturing the loaded labour rates for
each of the project’s resources, or resource groups, will allow you to
calculate the Budgeted cost of the work performed. The budget is simply the
total hours of effort in MS Project, to date, x the loaded labour rate. The AC
or ACWP is derived from the time tracking system and is calculated by
multiplying the total hours spent by each resource x the loaded labour rate for
that resource. The total AC is the sum of all the costs of all the resources. There
should be a report available from the time tracking system which will perform
these calculations for you. This will provide you and your sponsors with an
accurate picture of the project’s performance to budget.
Projects that involve the purchase of hardware or software
can either add these costs to the EV/BCWP, or report on them separately. In
either case, the project manager should agree upon the approach with the
Finance organization and also agree on whether to report these costs at the
time they are incurred (i.e. when the hardware and software are received), or
at the time they are paid for.
Time sheets bring a fringe benefit: they will show you when
your project is being delayed due to resources spending unplanned time on other
projects or activities. Work that is late, or is being finished at the desired
rate may be affected by the responsible team member not spending sufficient
time on the project. Simply compare the time that the time tracking system
tells you the resource has spent on your project with the time your MS Project
file. Any discrepancy explains why your work is not getting done on time.
A good time sheet tracking system should capture the loaded
labour rate for all project resources and support the reporting for CPI and
investigative purposes that you need. You should also be able to categorize
resources, activities, and project phases. The system should also support a
project administrator assigning resources to the project, closing out
activities and project phases and un-assigning resources from the project. You
need these safeguards to protect you from people charging time to your project
who have no business doing so. Remember that project reports the system is
capable of producing will be viewed by executives outside the project and your
project reporting needs to be reconcilable with that reporting.
Time sheets may not be feasible for every software
organization. Often, the cost of this reporting tool cannot be justified by the
benefits it brings to the project. When you are fortunate enough to be in an
organization that implements a time tracking system, support it by ensuring
that your project information, including resources assigned to your project, is
accurately captured in the system and your project team faithfully enters their
time in the tool when they should. In return, ask for the ability to generate
the type of reporting that your project communications plan calls for.
|