Gate Decisions
Many courses on project management leave one with the sense
that reaching a decision on moving a project forward to the next phase at agate meeting is a straightforward step: either the previous phase has delivered
everything planned for delivery and resources are in place to begin the next
phase, or they have not been delivered and/or resources are not in place. In
reality this state of "black or white" is almost never encountered in
a project and the project manager must deal with shades of gray and nuances in
coming to the decision.
Let's first address the question of available gate
decisions. There are actually 3 decisions available to you: pass, pass
contingent on an action or actions, and fail. The first 2 decisions enable all
or part of the work on the next phase to begin. The last one means that the project
schedule be delayed until the gate passes, or the project is aborted. Delaying
the schedule usually means additional costs and may not be palatable to your
customer or client. For this reason, an outright failure should be a last
resort. Canning a project which does not have a chance of delivering the sought
after benefits is the right action to take but you need to make absolutely
certain this is the case before proposing it as an outcome of a gate meeting.
You will want to discuss this with the project's executive sponsor or steering
committee before unleashing it at the gate meeting.
There are more than 2 "right" decisions that can
be reached at your gate meeting. This follows from the fact that not all
criteria can be viewed as black or white. Project managers who choose to view
gate meetings in simplistic terms will fail to spot opportunities to move the
project forward and address problems preventing the project from meeting its
goals and objectives. Recognizing that something other than an unqualified
meeting of each criteria the decision depends on is possible, while still
moving the project forward is a necessary strategy. Being flexible here will
move your project forward where being inflexible will waste time and money.
Think of it this way; a gate where every deliverable has
been completed calls for perfect planning and execution! Having all the
resources in place necessary to execute the next phase not only calls for
perfect planning and execution, it also calls for a perfect prediction of the
future.
Let's examine the criteria for passing the gate first. Gating
criteria for the final gate of the project is a special case (there is no
"next" phase for one thing), so we'll deal with that gate at the end
of this article. The criteria for every other gate can be logically divided
into 2 categories: previous phase deliverables and next phase resources. The
deliverables should be complete and delivered to the project. Those that are to
be given over to the project's customers or clients should be accepted and
those that are internal to the project should be ready for work in the next
phase. Must every deliverable that was planned for in the current phase be
completed before the project can move forward with the next phase? Obviously
not. Are there any deliverables that must be complete? Obviously. The trick is
to distinguish the "deal breakers" from the non-critical
deliverables. Deal breaking deliverables should be those that meet the
following criteria:
- A deliverable that prevents work beginning on
the next phase
- A deliverable that would cause significant extra
work in the next phase
- A set of deliverables that meet the above
criteria
Projects which are significantly enough behind schedule to
warrant altering the schedule should cause the schedule for the gate to slip,
the project manager should never go into that meeting without having prepared
stakeholders for this outcome. Even when a failed gate necessitates a slippage, you should plan to
begin as much of the next phase's work on time as possible so as to
waste the least possible time and money. The objective should be to identify the
corrective action before the gate meeting, or at least to have the corrective
action identified and communicated to the stakeholders before the meeting so
agreement on it can be reached at the gate meeting.
- A similar list of criteria can be identified for the next project
phase:
- A key human resource is unavailable to begin
work on the next phase
- A key resource or tool is unavailable to the
next phase
- A significant number of human resources or
materials is unavailable to the next phase
- Key training for work on the next phase has not
been delivered
- The plan for the next phase is not in place, or
has not been approved
Failure to meet any of these criteria would cause the gate
to fail. Failure to meet any of these criteria would also mean that the
schedule would slip. The same approach should be taken with a schedule slippage
as is taken with the previous phase.
Assuming that your project has produced all the key
deliverables planned and they have been accepted by your customers, or they are
available for work in the next phase, the gate should be passed. The pass may
not be unconditional, if there is any work that must be done to complete any
planned deliverables, or any work that must be completed to make resources or
materials available to the next phase the pass should be made contingent on
these being completed. To this end the project manager should keep an action
register for the gate meeting (either a separate register or the project action
register), the necessary actions identified and assigned, and a due date set.
The project manager should follow up with the stakeholders and keep them
informed as action items are completed and finally when all actions have been
completed and the gate passes unconditionally. Examples of deliverables that
should not fail a gate might include failure to install one of 100 outlets in a
house to complete electrical work, or failure to bring an ATM on-line for a
project delivering 1400 installed ATMs.
There are few guidelines to use to determine the criticality
of a deliverable so the project manager may have to take guidance from the
decision makers on how critical the deliverable is and perception may play an
important role in making that decision. The project manager should not sweat a
decision that a deliverable they regard as minor is a key one to the
stakeholders. Keep in mind that the difference between a contingent pass and a
fail is typically an additional gate meeting to be held when the critical
deliverable is ready.
Resources and materials for the next project phase are even
more forgiving than deliverables from the previous phase. To begin with, only
those resources and materials that are required for work to begin immediately
following the gate need to be in place. Those that are required for work
scheduled to begin at a later date need only be on track to meet those dates.
What is necessary to pass the gate is the plan for the next phase. Without this
plan, the gate should fail and only pass when the plan is ready. An example of
a non-critical resource or material might be failure to train 1 of 100 QA
testers, or the lack of 50 feet of 5/8" copper pipe out of a total of
5,000 feet. Projects that fail on this
scale should be given a pass contingent on the deficiency being made up.
Actions should be identified and tracked as previously described. Projects
where the stakeholders feel strongly that the resource or material missing is
critical to the project should be failed and a subsequent gate meeting held and
the gate passed when the deficiency is made up. Critical materials or resources
should only include those required immediately after the gate meeting.
Gate meetings which mark the closeout of the project are a
special case. There will be no next project phase so this category of gating
criteria can be ignored. Since the decision is whether to close the project out
or not, more emphasis will be placed on deliverables having been put into the
hands of the customer and accepted. This decision may be driven by the
statement of work; the criteria for acceptance of all the project deliverables
may be spelled out in the Statement of Work (SOW) and your deliverables have
either all been accepted and you are ready for closeout, or they have not and
you are not ready.
You should ensure that all conditions in the SOW are met on
time where there will be a penalty incurred for late closeout. Don't hesitate
to delay a closeout gate meeting otherwise. There will be no extra costs or
schedule slippages incurred by delaying the gate; resources who have completed
their work can be disengaged and only those necessary to finish incomplete work
retained. You should come to an agreement ahead of this meeting on what
constitutes a sufficient state of completeness to pass the gate and issue final
payments, if this is not spelled out in the SOW. Be prepared to decide on a
conditional pass where there is little work left to do. Don't re-schedule a
meeting just to inform everyone that the final outlet has been installed in the
new house and you are now in a position to pass the gate unconditionally.
Final Thoughts
The project manager should keep in mind that the most
important decision to the entity that is paying for the project is whether
there is a valid business case for doing the project. The initial decision is
always that it is, otherwise there would be no project. The business case needs
to be validated throughout the project, not just at gate meetings. The project
should be phased out as soon as the business case is no longer valid, or it
becomes apparent that the project is not feasible. This decision is greater in
scope than the gate meeting so it should be made outside that forum.
Decisions on whether the project is ready to proceed to the
next project phase are appropriate for the gate meeting. These decisions should
always be made in the context of a project with a valid business case and the
decision should enable the project to deliver the benefits promised by the
business case for a minimum amount of money and in as little time as possible. Any
decision involving a failure will cause a subsequent gate meeting to be
scheduled and the decision makers re-convened; this should only be done in
extreme circumstances. Most decisions will include some form of follow up that
ties up the loose ends that prevent the project from being 100% ready. The
project manager should be ready for this and steer the decision towards the
most practical decision. It is very likely that the decision which best suits
your project will be a conditional or contingent pass as it is unlikely that
all work has been completed to the customer's satisfaction. This is especially
true in large, complex projects. Be prepared to identify the actions necessary
to complete the work to the customer's satisfaction and capture these actions
in the action register while informing stakeholders of the conditional pass and
the actions necessary to reach completion.
The tips and tricks described here are all in alignment with
the information in the Integration Management knowledge are of the PMBOK. I
would recommend that any project manager who has not become certified as a PMP®
(Project Management Professional take the time to take PMP® Exam Preparation
training, or a PMP® Course and sit the exam. The three O web site contains an
excellent product, AceIt, which has helped PMs from around the world pass their
exams.
|